Three days of scope, one working day, occupied school

Denver metro · occupied K-12 campus · 2026

The original contractor fell through and the replacement plant was on its way. We took the call, matched the schedule, and cleared the room in a day.

2 × 7-section cast ironBoilers
2Expansion tanks
Flue, pump motors, pipingAlso
3 daysScheduled
1 working dayDelivered

The job

What we walked into

A mechanical contractor lost its demo crew with the new boilers already ordered and a school in session. The room had two seven-section cast iron boilers, two expansion tanks, the flue, pump motors and the piping between them, and it had to be empty before the install could start.

The approach

How it went

  • Verbal authorization, photos and a start time the same day, with the scope confirmed in writing.
  • Crew of three with full floor protection and the haul route cleared before the first section came off.
  • Sectioned both boilers, rigged the tanks and flue, pulled the motors, cut the piping at the agreed points, and hauled everything through the existing building paths.
  • Broom-clean turnover, photographed before and after, and the room back to the school two days early.

The result

Handed back

Three days of scope done in one working day inside an occupied school, no incident, and a new client relationship that has already produced the next call.

Before, during, after

The record

Client and site names withheld until written approval. Photographs are BCK job documentation.

Before: Cast iron boiler plant
BeforeCast iron boiler plant
Before: Expansion tanks and piping
BeforeExpansion tanks and piping
Before: Second boiler and flue
BeforeSecond boiler and flue
Before: Pump motors and runs
BeforePump motors and runs
After: Room cleared the same day
AfterRoom cleared the same day
After: Swept and handed back
AfterSwept and handed back

What the client got

The closeout

Scope-of-work completion verification, a captioned photo record by work area, recovery documentation where refrigerant was involved, and a certification of completion signed by both managing members. Delivered with the final invoice.

Services on this job

All projects

Boilers. Chillers. Mechanical systems.
We make them disappear.

A range in about a minute, or a site walk and a written proposal within 48 hours. Either way you're talking to an owner.

Call (303) 641-1012 Get an estimate