Three days of scope, one working day, occupied school
Denver metro · occupied K-12 campus · 2026
The original contractor fell through and the replacement plant was on its way. We took the call, matched the schedule, and cleared the room in a day.
The job
What we walked into
A mechanical contractor lost its demo crew with the new boilers already ordered and a school in session. The room had two seven-section cast iron boilers, two expansion tanks, the flue, pump motors and the piping between them, and it had to be empty before the install could start.
The approach
How it went
- Verbal authorization, photos and a start time the same day, with the scope confirmed in writing.
- Crew of three with full floor protection and the haul route cleared before the first section came off.
- Sectioned both boilers, rigged the tanks and flue, pulled the motors, cut the piping at the agreed points, and hauled everything through the existing building paths.
- Broom-clean turnover, photographed before and after, and the room back to the school two days early.
The result
Handed back
Three days of scope done in one working day inside an occupied school, no incident, and a new client relationship that has already produced the next call.
Before, during, after
The record
Client and site names withheld until written approval. Photographs are BCK job documentation.
What the client got
The closeout
Scope-of-work completion verification, a captioned photo record by work area, recovery documentation where refrigerant was involved, and a certification of completion signed by both managing members. Delivered with the final invoice.