Boiler & Chiller Killers HVAC demolition specialists · Denver
Boiler demolition · K-12 campus

Two 4-million-BTU firetubes, six expansion tanks, three days

Denver · public school mechanical room · 2026

A school-district boiler room under a mechanical contractor's coordination: two 4M BTU firetubes, six expansion tanks hung from the ceiling, a heat exchanger and the piping between them, with an abatement crew working the same building.

2 × 4M BTU firetubeBoilers
6Expansion tanks
1Heat exchanger
3Working days
District standardTurnover

The job

What we walked into

Firetubes don't come apart; they get cut, and the pieces have to fit the path out of a basement mechanical room. Six expansion tanks overhead and a heat exchanger meant rigging from above and below in the same space, while the project's asbestos abatement ran on its own schedule that ours had to respect.

The approach

How it went

  • Cut the piping at the termination points agreed with the mechanical contractor and left them ready for the new plant.
  • Sectioned both firetubes into pieces sized for the route out; rigged the expansion tanks down from the ceiling one at a time.
  • Sequenced the work around the abatement contractor so neither crew waited on the other.
  • Segregated scrap and debris streams, protected the floor and area, and swept the room before handing it back.

The result

Handed back

Room cleared and documented in three working days to the district's site standard, on the mechanical contractor's schedule for the new plant.

Before, during, after

The record

Client and site names withheld until written approval. Photographs are BCK job documentation.

Before: Firetube number one
BeforeFiretube number one
Before: Second firetube and piping
BeforeSecond firetube and piping
Before: Six expansion tanks overhead
BeforeSix expansion tanks overhead
Before: Heat exchanger and piping runs
BeforeHeat exchanger and piping runs
Before: Boiler nameplate
BeforeBoiler nameplate
During: Sectioning in process
DuringSectioning in process
After: Cleared and swept
AfterCleared and swept

What the client got

The closeout

Scope-of-work completion verification, a captioned photo record by work area, recovery documentation where refrigerant was involved, and a certification of completion signed by both managing members. Delivered with the final invoice.

Services on this job

All projects

Boilers. Chillers. Mechanical systems.
We make them disappear.

A range in about a minute, or a site walk and a written proposal within 48 hours. Either way you're talking to an owner.

Call (303) 641-1012 Get an estimate